Date of start : 05.2011
Duration : 10 months
Surface : 3000 m2
Number of employees : 4
The scope of work involved :
-
Scaffolding setting
-
Dismantling of flashings and gutter system
-
Demolition of the old cover
-
Execution of the new cover battening
-
Execution of cover and installation of gutter system
-
Thermal insulation of mineral wool